First-Time Sign Buyer Series: #3 – What Is the Typical Timeline for Designing, Manufacturing, and Installing a Sign?

When investing in signage, one of the most common questions is: “How long will it take to design, manufacture, and install my sign?” The answer depends on various factors, such as the type of sign, the complexity of the design, and the permitting process. At Green Sign Company, we’re committed to providing a seamless experience while keeping you informed every step of the way. Let’s break down the typical timeline for signage projects.

1. Initial Consultation and Design (1-3 Weeks)

The process beings with understanding your needs and vision. During this phase:

  • Consultation: We discuss your goals, brand identity, and the purpose of the sign. This step includes site surveys and gathering measurements if necessary.
  • Concept Development: Our design team creates initial concepts, incorporating your branding elements, desired materials, and any specific requests.
  • Revisions and Approval: We collaborate with you to refine the design until it’s perfect. Depending on the number of revisions, this stage can take anywhere from a few days to a couple of weeks.

2. Permitting and Approvals (2-8 Weeks)

For most exterior signs, local regulations require permits before installation. The timeline for obtaining permits varies by location:

  • Research: We ensure the design complies with zoning laws and building codes.
  • Submission: Permit applications are submitted to the appropriate local authorities.
  • Approval: Some jurisdictions process permits quickly, while other may take several weeks.

3. Manufacturing and Fabrication (2-6 Weeks)

Once the design is finalized and permits are approved, the manufacturing process begins:

  • Material Sourcing: High-quality materials are selected based on the design specifications.
  • Production: Our skilled team fabricates the sign, incorporation elements like illumination, dimensional lettering, or custom finishes.
  • Quality Control: Every sign undergoes rigorous checks to ensure durability and accuracy.

4. Installation (1-3 Days)

The final step is bringing your sign to life:

  • Scheduling: We coordinate with you to schedule the installation at a convenient time.
  • Site Preparation: For larger signs, this may involve excavation or foundation work.
  • Installation: Our experienced technicians install the sign, ensuring it’s securely placed and functioning properly.

Factors That Can Impact the Timeline

  • Complexity: Custom designs or large-scale signs may take longer to produce.
  • Weather: adverse conditions can delay outdoor installations.
  • Permit Delays: Some municipalities have lengthier approval processes.
  • Revisions: Extensive changes to the design can extend the timeline.

Typical Overall Timeline

Here’s a general estimate for common types of signs (Please note that these timelines are ESTIMATES ONLY):

  • Small Interior Signs: 2-4 Weeks
  • Exterior Non-Illuminated Signs: 4-8 Weeks
  • Illuminated or Custom Signs: 8-12 Weeks
  • Large-Scale or Monument Signs: 12-16 Weeks

The timeline for designing, manufacturing, and installing a sign depends on many factors, but a well-planned process ensures a successful outcome. At Green Sign Company, we pride ourselves on delivering high-quality signage while adhering to realistic timelines. Our team’s expertise ensures every step–from design to installation–is handled efficiently and professionally. If you’re ready to start your signage journey, contact Green Sign Company today! We’ll guide you through every step to bring your brand to life!